Brownstones Construction Photos, Calgary Home Builder, Airdrie Home Builder

Construction Update: The Brownstones

Time really flies when you’re making progress! Another week by, and more updates to bring those awaiting their new home in The Brownstones at Sage Meadows. Here’s where our crews are at in the construction phase:

Block 5’s stone tile has been 95% completed. In addition, the rear of the block has completed paper and is wired, and the next step in that process will be to start the stucco scratch coat.
Also on block 5, the rear garages have been framed, and now our construction crews will begin pouring the concrete floor in the garages.
Block 6 is in the process of having the rough-ins installed. Our crews have now completed the foundation pouring for the garages, and next up will be to start installing the exterior insulation.

We are in stages two (block 6) and three (block 5) of the five stages of development we undergo to build a new home. Here’s a look at the overall construction process:

Stage 1 – Excavation and Foundation

At this point, your home is staked out and the land is prepared for construction. Excavation is completed at this time (the removal of topsoil for construction), and concrete slabs, which will support the foundation walls, are formed and poured. Utilities like water, electricity, telephone and cable might be brought in as well.

The walls for the foundation will be erected, insulated and damp-proofed. Weeping tiles are installed, which drain ground moisture away from the home. A municipal inspection will be completed before the perimeter is filled as well.

Stage 2 – Framing and Lock-Up

At this phase of the development, exterior walls are framed and covered in exterior sheathing. The framework is actually built on the floor, one wall at a time, and then lifted into place. Roof trusses will also be brought in at this time, and installed as quickly as possible to prevent accidental damage as work progresses on the lower areas of the home.

The windows and doors will be installed, as well as the basement floor. Rough-ins are completed for electrical and plumbing services and the ductwork for HVAC is also installed.

Stage 3 – Insulation/Drywall

The key to the next couple phases of construction is proper scheduling, as a great deal of work happens during this time period. At this point, insulation of the exterior walls and roof will be done, with a vapour barrier applied (to keep out moisture). Another municipal inspection will be completed as well, and then drywall will be installed.

Stage 4 – Finishing Interiors and Exteriors

The heating and cooling systems, including fireplaces, will be installed at this point. The walls and ceilings of the home are painted, flooring is laid and the bathroom cabinets are installed. Final interior touches are completed: plumbing and electrical finishes are installed, trim is applied and doors are hung.

The exteriors are finished at this phase as well; siding is applied, eavestroughing is installed and porches/decks are built. The final lot grading will be complete, and the driveway and walkways will be poured.

Stage 5 – Pre-Possession to Possession

At this stage, finishing touches and clean-up will be done. With Genesis, you’ll do a walk-through of your home, which is perhaps the most exciting part, since you’ll get to see it for the first time. This is your opportunity to get anything fixed up or sorted out before you take possession.

Approximately 35 days prior to possession, you’ll receive a possession letter and you’ll have a short to-do list before move-in day. On the date of possession, you’ll be handed the keys—the home is now yours!

If you’re not familiar with some of the lingo we’ve used, check out our Construction Glossary. Whether you’re waiting for your new home in The Brownstones, or are just interested in learning more about this project or the community of Sage Meadows, you’ll find more insight on our website here.