Construction Update: The Brownstones

Time really flies when you’re making progress! Two weeks have gone by since our last update, and more updates to bring those awaiting their new home in The Brownstones at Sage Meadows. Here’s where our crews are at in the construction phase:

Block 5 is in the process of having the underground sprinkler system installed. Upon completion of that, crews will begin work on planting the trees and shrubs for this building.
Block 6 is in the mist of having the swale completed, and once that’s done, work will begin on the grading and loam for this building.

This is part of stage four of the five stages of development we undergo to build a new home, it’s one of the biggest phases of construction so a lot of work is done at this time. Here’s a look at the process:

If you’re not familiar with some of the lingo we’ve used, check out our Construction Glossary. Whether you’re waiting for your new home in The Brownstones, or are just interested in learning more about this project or the community of Sage Meadows, you’ll find more insight on our website here.